Intro
Media release
The Shire of Wyndham East Kimberley is contributing $3.9 million to the construction on top of the $10.6 million in State support. Previously, $500,000 of State funds and $150,000 of council funds went towards planning and design expenses.
The new pool is part of the Kununurra Aquatic and Leisure Centre re-development project that has already seen the building of a $3.2 million water playground that opened in 2022.
The new work will now include:
As part of the cost savings to make the 50-metre pool possible, the existing 25-metre pool will be demolished at the start of construction instead of the end, so the town will be without a pool for 18 months.
The change to the scope of the plan occurred due to community demand for the 50-metre pool option.
Construction is due to start in August 2024 and is scheduled for completion in December 2025.
Video (below): Architect's view of the proposed Kunnunurra Aquatic and Leisure Centre redevelopment. Video courtesy of Donovan Payne Architects